For example, she said, the environmental licensing process for a hydroelectric plant takes an average of 10 years, and the country has 27,000 regulations. In 2022, she said, more than 5,000 projects — including highways, railways, waterways, transmission lines, mineral pipelines, gas pipelines and fiber-optic cables — were stalled over licensing issues.